Written by Canadian Environmental Assessment Agency on 31 January 2014
Further to yesterday’s information , the Panel has issued a letter in response to Stillwater Canada’s Inc. request to suspend the environmental assessment process. The letter is available on the public registry at: http://www.ceaa-acee.gc.ca/050/documents/p54755/98244E.pdf. The Panel has [Read more]
Written by Canadian Environmental Assessment Agency on 30 January 2014
Dear Interested Parties, Please see the attached letter from Stillwater Canada Inc. requesting that the environmental assessment process, including the public hearing, for the proposed Marathon PGM-Cu Mine Project be suspended until further notice to allow the proponent to complete an evaluation of [Read more]
Written by Canadian Environmental Assessment Agency on 30 January 2014
The Marathon Joint Review Panel (the Panel) would like to draw your attention to two letters posted on the public registry: A letter from the Lake Superior Binational Forum, Environment North, Northwatch and MiningWatch Canada dated January 27/14, expressing concern regarding recent comments made [Read more]
Written by Canadian Environmental Assessment Agency on 23 January 2014
Interested Parties please be advised that on January 20, 2014, Stillwater Canada Inc. submitted its responses to the Additional Information Requests issued by the Marathon Joint Review Panel (the Panel) on September 30 and December 17, 2013. The responses are now available on the public [Read more]
Written by Canadian Environmental Assessment Agency on 20 January 2014
Please be advised that Colette Spagnuolo will be taking over as the Joint Review Panel co-manager for the Marathon Mine Project. Questions regarding the Project should be directed to either Colette at (613) 957-0541or Jeff Sewell at (705) 670-5872 or e-mail the Marathon Mine inbox [Read more]
Written by Environment Canada - Environnement Canada on 21 November 2013
Stillwater Canada Inc. has submitted a response to Supplementary Information Request No 11 – Cumulative Effects Assessment issued by the Joint Review Panel on August 30, 2013. The response is available on the public registry at the following link: Response to SIR [Read more]
Written by Canadian Environmental Assessment Agency on 31 August 2013
The Joint Review Panel has made a decision on the sufficiency of the Marathon Platinum Group Metals and Copper Mine Project Environmental Impact Statement and Additional Information. The decision is posted on the public registry as document #564 and can be found at the following link: [Read more]
Written by Canadian Environmental Assessment Agency on 24 May 2013
During the week of May 6, 2013, Stillwater Canada Inc. submitted additional responses to some of the information requests (IRs) issued by the Marathon Joint Review panel last November and December. The additional responses are as follows (a link to the posting on the registry is provided): Response [Read more]
Written by Canadian Environmental Assessment Agency on 06 May 2013
During the week of April 29/13, Stillwater Canada Inc. submitted additional responses to some of the information requests (IRs) issued by the Marathon Joint Review Panel last November and December. The additional responses received are outlined below with a link to the posting on the public [Read more]