Posts Tagged ‘Marathon PGM Cu Joint Review Panel’
Written by NewsWire on 31 January 2014
BILLINGS, MT — (Marketwired) — STILLWATER MINING COMPANY (NYSE: SWC) (TSX: SWC.U)(the “Company”) today announced that Stillwater Canada Inc has requested that the joint review panel suspend the Marathon project environmental assessment and panel hearings until further [Read more]
Written by Canadian Environmental Assessment Agency on 23 January 2014
Interested Parties please be advised that on January 20, 2014, Stillwater Canada Inc. submitted its responses to the Additional Information Requests issued by the Marathon Joint Review Panel (the Panel) on September 30 and December 17, 2013. The responses are now available on the public [Read more]
Written by Canadian Environmental Assessment Agency on 20 January 2014
Please be advised that Colette Spagnuolo will be taking over as the Joint Review Panel co-manager for the Marathon Mine Project. Questions regarding the Project should be directed to either Colette at (613) 957-0541or Jeff Sewell at (705) 670-5872 or e-mail the Marathon Mine inbox [Read more]
Written by Environment Canada - Environnement Canada on 21 November 2013
Stillwater Canada Inc. has submitted a response to Supplementary Information Request No 11 – Cumulative Effects Assessment issued by the Joint Review Panel on August 30, 2013. The response is available on the public registry at the following link: Response to SIR [Read more]
Written by Environment Canada - Environnement Canada on 05 November 2013
MARATHON, ON – Stillwater Canada Inc. has submitted responses to two Supplementary Information Requests issued by the Marathon PGM-Cu Joint Review Panel on August 30, 2013. Response to SIR 9 – Environmental Design Storm. Response to SIR 4 – COPC Loading Rates and Water Quality [Read more]
Written by Canadian Environmental Assessment Agency on 18 September 2013
MARATHON, ON – Louis LaPierre has tendered his resignation as Chair and member of the Marathon Mine Joint Review Panel for medical reasons: Original letter from Louis LaPierre: http://www.ceaa-acee.gc.ca/050/documents/p54755/94502E.pdf Marathon Mine Panel Co-Manager Marie LeGrow has [Read more]
Written by Canadian Environmental Assessment Agency on 31 August 2013
The Joint Review Panel has made a decision on the sufficiency of the Marathon Platinum Group Metals and Copper Mine Project Environmental Impact Statement and Additional Information. The decision is posted on the public registry as document #564 and can be found at the following link: [Read more]
Written by Canadian Environmental Assessment Agency on 07 March 2013
March 1, 2013, Stillwater Canada Inc. submitted responses to some of the Information Requests (IRs) issued by the Joint Review Panel last November and December. Responses have been received to the following IRs, and are available on the public registry at the links below: Project Description (IR [Read more]