Marathon PGM-Cu Joint Review Panel Update

Marathon PGM-Cu Joint Review Panel Update

Interested parties are reminded that the Marathon Joint Review Panel is requiring Stillwater Canada Inc. to provide monthly updates regarding the status of the work to update the project’s feasibility study and to respond to the Panel’s information request.  The Panel invites participants to [Read more]

Watchgroup Letters Posted to Marathon PGM-Cu Public Registry

Watchgroup Letters Posted to Marathon PGM-Cu Public Registry

The Marathon Joint Review Panel (the Panel) would like to draw your attention to two letters posted on the public registry: A letter from the Lake Superior Binational Forum, Environment North, Northwatch and MiningWatch Canada dated January 27/14, expressing concern regarding recent comments made [Read more]

Marathon PGM-Cu Joint Review Panel Update to Interested Parties – Availability of AIR Responses

Marathon PGM-Cu Joint Review Panel Update to Interested Parties – Availability of AIR Responses

Interested Parties please be advised that on January 20, 2014, Stillwater Canada Inc. submitted its responses to the Additional Information Requests  issued by the Marathon Joint Review Panel (the Panel) on September 30 and December 17, 2013.  The responses are now available on the public [Read more]

New Marathon PGM-Cu Joint Review Panel Co-Manager

New Marathon PGM-Cu Joint Review Panel Co-Manager

Please be advised that Colette Spagnuolo will be taking over as the Joint Review Panel co-manager for the Marathon Mine Project. Questions regarding the Project should be directed to either Colette at (613) 957-0541or Jeff Sewell at (705) 670-5872 or e-mail the Marathon Mine inbox [Read more]

Planning to Attend Marathon PGM-Cu Mine Public Hearing(s)? Documents You Should Review

Planning to Attend Marathon PGM-Cu Mine Public Hearing(s)? Documents You Should Review

The Joint Panel reviewing the Marathon PGM-Cu Mine project has set the date of the public hearing which will  commence February 20th in Marathon, ON.  The linked document (below) is meant to help participants prepare for the public hearing and answer some of the key questions that participants [Read more]

Revised Start Date for Marathon PGM-Cu Mine Project Public Hearing

Revised Start Date for Marathon PGM-Cu Mine Project Public Hearing

Please be advised that the Joint Panel reviewing the proposed Marathon Platinum Group Metals and Copper Mine project has announced a revised the start date for the public hearing.  The hearing will now begin in Marathon, Ontario on February 18, 2014, and will be completed within approximately 4 [Read more]

Joint Review Panel Issues Notice of Public Hearing – Marathon PGM-Cu Mine Project

Joint Review Panel Issues Notice of Public Hearing – Marathon PGM-Cu Mine Project

December 17, 2013 – The Joint Panel reviewing the proposed Marathon Platinum Group Metals and Copper Mine project today announced that it has received sufficient information to proceed to the public hearing. The hearing will begin in Marathon, Ontario on February 4, 2014, and will be completed [Read more]

Stillwater Responses to SIR No.5 ‘Hare Lake’

Stillwater Responses to SIR No.5 ‘Hare Lake’

Stillwater Canada Inc. has submitted response to Supplementary Information Request No 5 – Hare Lake  issued by the Joint Review Panel on August 30, 2013. The responses are available on the public registry at the following link: Response to SIR [Read more]

Stillwater responsdes to SIRs Issued Aug.30.2013

Stillwater Canada Inc. has submitted responses to two Supplementary Information Requests issued by the Joint Review Panel on August 30, 2013. Response to SIR  1 – Assessment of Alternative Rail Load-out Locations and Rail Shunting Noise Criteria Response to SIR  10 –  Human Health Risk [Read more]

Additional IRs Issued to Stillwater Canada for Response Prior to Public Hearing

Additional IRs Issued to Stillwater Canada for Response Prior to Public Hearing

The Marathon Joint Review Panel has issued additional information requests to Stillwater Canada Inc. for response prior to the public hearing.  Please note that the public hearing will not be scheduled until the Panel has determined that the Environmental Impact Statement (EIS) and responses to [Read more]

Joint Review Panel Decision RE: Sufficiency of Marathon PGM-Cu EI & Addn Info

Joint Review Panel Decision RE: Sufficiency of Marathon PGM-Cu EI & Addn Info

The Joint Review Panel has made a decision on the sufficiency of the Marathon Platinum Group Metals and Copper Mine Project Environmental Impact Statement and Additional Information.  The decision is posted on the public registry as document #564 and can be found at the following link: [Read more]

Marathon Joint Review Panel : IR’s Consolidated to Facilitate Public Review

Marathon Joint Review Panel : IR’s Consolidated to Facilitate Public Review

MARATHON, ON – In order to help facilitate your review of the information provided by Stillwater Canada Inc.  the Information Requests received between March 4, 2013 to June 26, 2013 have been consolidated into one webpage which can be found at the following [Read more]

Marathon Joint Review Panel – Availability of Additional IR Responses

Marathon Joint Review Panel – Availability of Additional IR Responses

Stillwater Canada Inc. has submitted 13 additional responses to information requests (IRs) issued by the Marathon Joint Review Panel last November and December. The additional responses are as follows (a link to the posting on the registry is provided): Response from Stillwater Canada to [Read more]

Marathon Joint Review Panel – Availability of Additional IR Responses

Marathon Joint Review Panel – Availability of Additional IR Responses

During the week of May 6, 2013, Stillwater Canada Inc. submitted additional responses to some of the information requests (IRs) issued by the Marathon Joint Review panel last November and December. The additional responses are as follows (a link to the posting on the registry is provided): Response [Read more]

Stillwater Submits Additional Responses to IRs by Marathon Joint Review Panel

Stillwater Submits Additional Responses to IRs by Marathon Joint Review Panel

During the week of April 29/13, Stillwater Canada Inc. submitted additional responses to some of the information requests (IRs) issued by the Marathon Joint Review Panel last November and December. The additional responses received are outlined below with a link to the posting on the public [Read more]