CEAAInterested Parties please be advised that on January 20, 2014, Stillwater Canada Inc. submitted its responses to the Additional Information Requests  issued by the Marathon Joint Review Panel (the Panel) on September 30 and December 17, 2013.  The responses are now available on the public registry at the links below.  Please note that the response to AIR #14 “Table of Commitments” will be posted to the public registry later today.

CEAR # 646 Additional Information Request # 1: Project Description – Mining Claims
CEAR # 647 Additional Information Request # 2: Location of Project Components within the Local Watersheds
CEAR # 648 Additional Information Request # 3: Methodology for Significance Determination
CEAR # 649 Additional Information Request # 4: Acid Rock Drainage / Metal Leaching Prediction and Mitigation
CEAR # 650 Additional Information Request # 5: Separation of Ore and Type 1 and 2 Mine Rock
CEAR # 651 Additional Information Request # 6: Hydrogeological Context of Temporary Type 2 Mine Rock Stockpiles
CEAR # 652 Additional Information Request # 7: Pit Water Quality
CEAR # 653 Additional Information Request # 8: Groundwater Seepage from the PSMF and MRSA
CEAR # 654 Additional Information Request # 9: Potential Effects on Rare Plants
CEAR # 655 Additional Information Request # 10: Fish and Fish Habitat – Additional Surveying and Data Collection
CEAR # 656 Additional Information Request # 11: Fish and Fish Habitat – Restoration of Streams 2, 3, and 6
CEAR # 657 Additional Information Request # 12: Conceptual Reclamation Plan
CEAR # 658 Additional Information Request # 13: Management and Mitigation of Type 2 Mine Rock
CEAR # 664 Additional Information Request # 15: Baseline Noise Levels
CEAR # 659 Additional Information Request # 16: Human Health Risk Assessment
CEAR # 660 Additional Information Request # 17: Acid Base Accounting
CEAR # 661 Additional Information Request # 18: COPC Loading Rates and Water Quality
CEAR # 662 Additional Information Request # 19: Impacts of PSMF Discharge to Hare Lake
CEAR # 663 Additional Information Request # 20: Assessment of the Alternative Rail Load-out Location in Schreiber, ON