RED ROCK Marina Construction – UPDATE
RED ROCK, ON – The construction of the Red Rock Marina building is progressing well. Sub-contractors have been preparing this building throughout the summer. It is our intention to have a construction completion date for the end of October 2012.
CONTRACTORS WORK PROGRESSION
Red Rock Local Construction Crew
The local construction crew consists of 9 employees and one Site Construction Manager. The work performed is ongoing with a progression of work as follows:
- Interior wall framing, 100% completed
- Exterior walls, roof, gable ends and mechanical mezzanine, 100% completed
- Drywall and interior insulating, 70% completed
- Window installation, 60% completed
- Door frames, doors and door glass installation, 40% completed
- Interior painting to start the week of August 27/12
Phase One – COMPLETED
- Site services/building concrete floor
- in-floor heating tubing)
Phase Two
- TP-12 Metal Roofing – (All-Tech Systems Inc) (100% completed)
- TP-14 Mechanical – (E.S. Fox Ltd) (plumbing, boilers, solar hot water system. 60% completed)
- TP-15 Electrical – (P.A. Grant Inc.) (wiring, receptacles, lighting, 79% completed)
Phase Three
- TP-06 Doors and Frames – (Quality Door) (70% completed)
- TP-09 Misc Metals – (Jet Welding) (100% completed)
- TP-16 Overhead Coiling Doors – (Superior Door Co.) (ongoing
Sub Contractors
- AEGUS Contracting (100% completed Bell Line to building)
- NORTEC Drywall Systems (70% completed drywall finishing)
- PIERCE FLORCRAFT Ltd (Flooring/Tiles/Ceramic bathroom tiles – ordered but not on site)
- TELECO Landline Systems (Telephone system – not on site yet)
- NORTHERN Decorating Supplies (All interior and exterior paint on site)
- WANSON Lumber (All windows have arrived and stored)