KWG REPORTS POSITIVE PRELIMINARY ECONOMIC ASSESSMENT OF BIG DADDY
Montreal, PQ– April 12, 2011 – A Preliminary Economic Assessment (PEA) study commissioned by KWG Resources Inc. (TSXV: KWG) on the Big Daddy Chromite deposit (Project) in the remote Ring of Fire area in the James Bay Lowlands of northern Ontario, recommends the Project be advanced to the Feasibility Study phase. KWG Resources Inc. owns a current 28% interest in the Project plus a 1% Net Smelter Royalty (NSR) on production from both the Project and the adjacent Black Thor and Black Label Chromite deposits, and has the option to increase its interest in the Project to 30%.
KWG President Frank Smeenk commented that, “The PEA results indicate the Big Daddy deposit, if developed, could provide compelling returns to the owners at present prices. The estimated undiscounted cash flow per presently outstanding KWG share over the life of the Project, from KWG’s interest alone, is $2.97 per share.” Please note, cash flow and NPV do not represent a fair market value of the project.
The Project as described in the PEA includes the development of a railway and power line to the site, an open pit mine and associated crushing plant and infrastructure. It is estimated that the pre-production construction would be completed over a 3 year time period and the open pit would produce a total of 25.35 million tonnes of indicated potentially mineable resource and 13.54 million tonnes of inferred potentially mineable resource of lump chromite mineralization, over a 16 year operating life. This scenario represents one of many development options for the Project. The PEA recommends that additional options be considered through marketing, transportation and mineralization processing studies to provide the preferred option for use in the definitive Feasibility Study. All dollar values unless otherwise stated are in Canadian Dollars and an exchange rate of $CDN:$US of 1.00 used.
- This estimate was based on a price of US$325 per tonne of lump chromite mineralization and an open pit shell produced using MineSight. A cut-off grade of 35% Cr2O3 was used.
- NPV estimates for KWG interest do not include NSR Royalty paid to KWG.
- Lump Chromite mineralization is material which has sufficient grade (i.e. greater than 35% Cr2O3 ) that smelting of the rock can be directly performed. Lower grade material (greater than 3.83% and less than 35% Cr2O3 ) would be stockpiled for possible processing in the future.
- Includes the Project’s 50% portion of estimated $900 million cost for railway construction.
The PEA includes a proposed railway which would extend approximately 350 kilometres from the mine and connect to the Canadian National Railway’s main line near the town of Nakina, Ontario. The construction cost for the railway line is the largest single capital expenditure for the project at an estimated cost of $900 million. The project returns are sensitive to the railway capital expenditures as they occur prior to the project entering operation. The PEA has assumed that the cost of the railway would be borne between the Project and other area projects presently under development or study for development and thus allocates 50% of the cost to the Project.
The sensitivity analyses conducted as part of the PEA indicated that if the lump chromite mineralization price increased to US$425 per tonne, the pre-tax IRR and NPV (8%) would be approximately 57.6% and $4.2 billion, respectively. KWG President Frank Smeenk stated that “This scenario, on an undiscounted basis, would increase KWG’s share of pre-tax cash flow to approximately $3.05 billion, or $4.78 per presently outstanding KWG share”.
The open pit would be mined conventionally using shovels and diesel powered haul trucks. The ultimate open pit would measure approximately 1.7 km long by 1.3 km wide by 570 metres deep. Approximately 1 billion tonnes of waste would be produced over the life of mine at an overall stripping ratio of 27:1. Product preparation would consist of crushing the lump chromite mineralization to minus 51 mm size, prior to trans-shipping by rail.
The PEA was prepared in conformance with National Instrument 43-101 by NordPro Mine & Project Management Services Ltd. (NordPro) of Thunder Bay, Ontario. The report was prepared by Brian LeBlanc, P. Eng. of Nordpro and NordPro Associate Malcolm Buck, P. Eng., each a “Qualified Person” under the Instrument and they have supervised the preparation of the information that forms the basis of the written disclosure in this news release. NordPro utilized the Micon International Limited resource model and estimate as reported in “Spider Resources Inc. and KWG Resources Inc. Technical Report On The Mineral Resource Estimate for the Big Daddy Chromite Deposit McFaulds Lake Area, James Bay Lowlands, Northern Ontario, Canada” dated March 30, 2010. The PEA uses Inferred Resources which are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. There is no certainty that the results predicted by this PEA will be realized. The mineral resources estimate could be materially affected by environmental, geotechnical, permitting, legal, title, and taxation, socio-political, marketing or other relevant issues.
The level of accuracy of the PEA is +/- 40 percent. The PEA report will be filed on SEDAR within 45 days from the date of this release.
MORE INFO
- For more information visit the KWG Resources Inc. website
- Follow KWG on Facebook: http://www.facebook.com/kwgresourcesinc
- Follow KWG on Twitter: http://twitter.com/kwgresources
- KWG’s YouTube: Channel http://www.youtube.com/KWGresources
- KWG’s Flickr account: http://www.flickr.com/photos/kwgresources